Total Questions 69
MCQ's 62
Short Question 07

Time 120 min
MCQ's were conceptual

Short Question were as under

Q.1: 'Demand for service is usually difficult to predict'
Comment on this statement in the light of aggregate planning ( 3 marks)

Q.2: How is inventory storage minimized in JIT system ( 3 marks )

Q.3: As a operational manager of ABC company, what do you think are the various measures that lead to good scheduling result ( 3 marks )

Q.4: Find maximin, maximax and lapalace

small 10000 8000
medium 12000 20000
large 18000 15000 ( 5 marks)

Q.5: Comment on the statement: 'Use of over time /slake time is less severe method for changing capacity then hiring and laying of workers' ( 5 marks )

Q.6: Consistent high quality of JIT is main focus of JIT. How JIT aim at predicting 'Quality at Source' ( 5 marks )

Q.7: Senior managment of a service firm has initiated a short term project of building a new facility of a designated area. What will be the responsibilities and qualification of a project manager regarding this project ( 5 marks)

No comments: